School Condition Building Programme 2024-2025: Roofing Works at 5 Schools

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decisions:

RESOLVED:

 

That the Cabinet approves:

 

1)    The award of a building works contract to CWG Group Ltd for works outlined in this report at Bourne Primary School, Whitehall Infant School and Whiteheath Infant School at a cost of £1,148,624;

 

2)    The award of a building works contract to CWG Group Ltd for works outlined in this report at Newnham Infant School and Hayes Park School at a cost of £1,487,810 and;

 

3)    The capital release request of £3,057,394 from the 2024/25 School Conditions Building Programme budget relating to roofing works at 5 schools, Newnham Infant School, Bourne Primary School, Whitehall Infant School, Whiteheath Infant School and Hayes Park School, and associated costs.

 

Reasons for decision

 

As part of the Council’s programme to improve school buildings, Cabinet agreed contracts for roofing works at 5 schools - Newnham Infant School, Bourne Primary School, Whitehall Infant School, Whiteheath Infant School and Hayes Park School.

 

Alternative options considered and rejected

 

None.

 

Relevant Select Committee

Corporate Resources & Infrastructure

Expiry date for any scrutiny call-in / date decision can be implemented (if no call-in)

Cabinet’s decisions can be called in by a majority of the Select Committee by 5pm, 3 June 2024. If not called-in, it can be implemented after this time/date.

Officer(s) to action

Michael Naughton

Directorate

Place

Classification

Private - Whilst the Cabinet's decisions above are always made public, the officer report relating to this matter is not because it was considered in the private part of the meeting and contained information relating to the financial or business affairs of any particular person (including the Authority holding that information) and the public interest in withholding the information outweighed the public interest in disclosing it in accordance with Section 100(A) and paragraph 3 of Part 1 of Schedule 12 (A) to the Local Government Act 1972 (as amended).

 

 

Publication date: 24/05/2024

Date of decision: 23/05/2024

Decided at meeting: 23/05/2024 - CABINET

Effective from: 04/06/2024