Concerns, comments and suggestions raised by
petitioners at the meeting included the following:
-
Mr Ahmad Ghaffary spoke
on behalf of the petition submitted to the Council.
- The petitioner
circulated photographs to show the condition of the road and
pavement surface on Cottage Close.
- Residents had raised
concerns about the condition of the road over a long period of time
and felt that these concerns had fallen on deaf ears.
- Council Officers had
not conducted a site visit for Cottage Close and would therefore
not have first-hand knowledge of the condition of the road
surface.
- Petitioners had been
informed that the re-surfacing of the road would take place but
that this work was not likely to be undertaken until March 2013.
Petitioners stated that this had previously been agreed for October
2012.
- The pictures provided
showed that both the road surface and the pavement were in a state
of disrepair. It was noted that the area around a fire hydrant was
particularly dangerous for pedestrians.
- The elderly had to
walk on the road due to the poor condition of the
pavement.
Councillor Keith Burrows listened to the concerns of
the petitioners and responded to the points raised:
- A site visit had
taken place at Cottage Close. This was standard practice for
Officers writing reports on the condition of road surfacing and
determining whether pot holes are deeper than the emergency
intervention level of 40mm.
- The site did not
exceed the emergency intervention level of 40mm so Cottage Close
would not be considered as in need of immediate repair. However,
the road did have a number of fretting areas.
- The projected date of
March 2013 for the surfacing of this road was partly due to an
issue with the provider of a new type of road surfacing. The new
surfacing could only be laid in temperatures over 5°C which
meant that laying would have to stop between November 2012 and
March/April 2013. The Council was in the process of sourcing a new
product that could be laid in colder temperatures. If this could be
sourced, it might be possible for the road to be resurfaced earlier
than March.
- Prior to the
re-surfacing of the road, the Council would monitor the condition
of the road to assess whether it fell within the emergency
intervention levels.
- It was noted that
although the pavement was not part of the petition, the photographs
provided by the petitioners to show the poor condition of the
surface were of enough concern for officers to investigate
immediately. A damaged area around a fire hydrant was of particular
concern.
Officers advised
that:
- Cottage Close would
be resurfaced with Micro Asphalt but that the road would not be
entirely resurfaced; some areas would be planed back and given a
new surface but others would only be patched.
RESOLVED - That the Cabinet Member:
1.
Considered the petitioners’ request and discussed
with them in detail their concerns regarding the condition of the
carriageway surface.
2.
Instructed officers to place Cottage Close on to the
list for roads being considered for treatment in a future
resurfacing programme.
Reasons for recommendation
The existing carriageway
surface had started to show signs of deterioration to the extent
that shallow fretting had taken place in isolated areas of the
carriageway. The failure is due to the natural ageing of the
bitumen surface, which was slowly disintegrating after an estimated
life of 5 to 15 years. Past patching
had filled some of the worst fretting but only as a medium term
measure. The road profile was
“bumpy” in places and construction joints had opened at
a number of locations. Resurfacing using a micro surfacing would
improve the visual appearance of the road and improve the ride
quality. Officers would also undertake
isolated repairs to the footway, which fall within the
Council’s intervention levels.
Alternative options considered / risk
management
Further patching works:
However, this option had been discounted due to the shallow depth
of the existing bitumen surface dressing. The road had a thin
asphalt overlay over a concrete structure. In such a construction
it was difficult to patch the surface and consistently ‘tie
in’ to the existing surface level. Delaying or not
undertaking certain schemes may have placed additional pressure on
the Council’s financial resources if highway permanent
repairs were not implemented in a timely manner. In many instances,
the delay of schemes may also have had safety implications with
possible consequent impact on the public liability insurance
budget.
Officers considered that the
carriageway surface was beyond normal patching repair and that
resurfacing using a micro surfacing material was the most
economical option available to restore a watertight smooth
surface.